Skip to main content
Book a call — £89
Menu

Lump Sum Construction Contracts UK: Fixed Price Guide

We're not a law firm — we help you find the right legal support. For advice on your situation, speak to a legal adviser or find a solicitor.

Part ofConstruction

Updated June 2026 · England & Wales
If you are about to engage a builder for a defined project, a lump sum contract is one of the most common arrangements you will come across in the UK. The idea is simple on the surface: the contractor quotes one fixed price for the whole scope of work, and that is what you pay on completion. In practice, there is a lot more sitting underneath that headline number, from how the scope is described, to what happens if the client changes their mind halfway through, to who carries the cost when the ground turns out to be worse than expected. This guide walks through how lump sum contracts work in a UK construction context, the risks on each side, and the points I would want any client to understand before signing one.

What this document is

A lump sum contract, sometimes called a fixed-price or stipulated-sum contract, is an agreement where the contractor commits to completing a defined scope of work for a single agreed price. Unlike cost-plus or remeasurement contracts, the price does not move up and down with actual expenditure.

The contractor takes on the job of estimating labour, materials, plant, overheads and profit, and wraps it all into one number. In the UK, lump sum arrangements are often used on projects where the design is reasonably complete before work starts, because the contractor needs a clear picture of what is being built to price it properly.

Standard form contracts such as the JCT suite and, in some cases, NEC options, include lump sum structures. The price can still change, but usually only through defined mechanisms like variation clauses, relevant events, or compensation events, rather than through open-ended reconciliation of actual costs. That structure is what gives the client budget certainty and puts cost management firmly on the contractor's shoulders.

How to use this document

  1. Define the scope of work properly. Before any price is agreed, both parties need a clear, detailed description of what is being built, to what specification, and to what standard. Drawings, specifications, and schedules of work should be referenced in the contract. A vague scope is the single biggest cause of disputes on lump sum jobs.
  2. Agree the contract sum and payment schedule. The total price should be set out in writing, along with how and when it will be paid. Most UK construction contracts use interim payments tied to progress or valuation dates, with a final payment on practical completion and a release of retention after the defects period. The Construction Act sets minimum payment rules that apply to most construction contracts.
  3. Set out the variation and change control process. Even on a fixed price, clients often want changes once work begins. The contract should explain how variations are instructed, how they are priced, and how they affect the programme. Without a clear process, every change becomes an argument about money and time.
  4. Deal with risk, delay and extensions of time. The contract should identify which risks sit with the contractor, which sit with the client, and what triggers an extension of time or additional payment. Ground conditions, delays caused by the client, and statutory changes are common flashpoints. A good contract spells these out rather than leaving them to chance.
  5. Plan for completion, defects and dispute resolution. Cover practical completion, the defects liability period, retention, and how disputes will be handled. Most UK construction contracts provide for adjudication under the Construction Act, which gives a quick decision during the works. Getting these final clauses right matters as much as the price itself.

Common questions

If you're dealing with this kind of situation, speak to an experienced legal adviser who can walk you through it — from £89.

Common questions

Q Is a lump sum contract the same as a fixed price contract?
In everyday UK construction language, yes, the terms are used interchangeably. Both describe an agreement where the contractor carries out a defined scope of work for a single agreed price. Strictly speaking, a lump sum contract can still allow adjustments for variations, prime cost sums, provisional sums, or extensions of time. So the price is fixed at the outset, but it is not always completely immovable.
Q Who carries the risk of cost overruns on a lump sum job?
In most cases, the contractor. If materials cost more than expected, or the work takes longer than estimated, the contractor usually absorbs that cost because the price has been agreed. The client's risk is more limited, but it still exists around variations they instruct, delays they cause, and risks the contract specifically allocates to them, such as certain ground conditions.
Q When is a lump sum contract not a good idea?
Lump sum works best when the design is well developed before construction starts. If the scope is still evolving, or the ground conditions are unknown, contractors either refuse to fix a price or load it heavily with contingency. In those situations, a remeasurement contract or a target cost approach may give a fairer outcome for both sides and reduce the pressure to cut corners.
Q Can the price change after the contract is signed?
Yes, but only through the mechanisms the contract allows. Typical examples include variations instructed by the client, claims for loss and expense following a qualifying delay, adjustments for provisional sums, or changes in statutory requirements. The contractor cannot simply increase the price because their costs went up, which is why accurate pricing at tender stage matters so much.
Q Do UK construction contracts have to be in writing?
The Housing Grants, Construction and Regeneration Act 1996, often called the Construction Act, applies to most construction contracts regardless of whether they are written or oral. However, its payment and adjudication provisions are much easier to enforce when the terms are set down in writing. For anything beyond a very small job, a written contract is strongly advisable.
Q What is a provisional sum in a lump sum contract?
A provisional sum is an allowance included in the contract price for work that cannot be fully specified or priced at the time of signing. Once the work is defined, the provisional sum is replaced with the actual cost, and the contract sum is adjusted accordingly. It is a useful way to keep a project moving while leaving room to pin down certain elements later.
Q How are disputes usually resolved under a UK construction contract?
Under the Construction Act, either party to a qualifying construction contract has the right to refer a dispute to adjudication at any time. Adjudication is a fast process designed to give a binding decision within weeks, so work can continue. Parties can still take disputes to arbitration or court afterwards, but in practice many disputes settle once the adjudicator has decided.
If you're dealing with this kind of situation, speak to an experienced legal adviser who can walk you through it — from £89.

Sources

This guide is based on primary UK law and official guidance.

Brad Askew, Solicitor (non-practising)

Written & reviewed by

Brad Askew Solicitor (non-practising)

Brad is on the roll of solicitors of England & Wales but does not hold a practising certificate and does not provide legal advice. LegalDocuments.co.uk is not a law firm and does not provide regulated legal advice.

Legal disclaimer
This article is for general information only. It is a tool to help you find your way — not legal advice, and not a substitute for speaking to a qualified adviser about your situation.